UK consultant Turner & Townsend is warning that the UK industry should beware insolvencies as demand weakens and margins are squeezed.
Its latest market analysis points to falling demand, rising input costs and lower margins, and notes that the number of construction insolvencies far outstrips those in retail.
With confusion persisting over the Brexit withdrawal agreement, client organisations should prepare for “supply chain distress” and take steps to pre-empt, manage and neutralise this risk, the consultant said.
Contractors expect tender prices to increase 2.9% in 2019, outstripped by increasing materials costs of 5.3% and labour costs rising 4.5%.
Only 28.4% of contractors expect the market to improve, against 42.1% prior to the Brexit vote in June 2016.
Official data show that construction witnessed the highest insolvency rate of any UK economic sector, with 2,924 insolvencies recorded in the 12 months to the end of September 2018.Â
This figure is 28.8% higher than the UK’s struggling retail sector.
The underlying cause is weakening demand in construction, Turner & Townsend says. Despite a small 3.4% rise on the previous quarter, new orders in Q3 2018 were down almost a third (30.8%) on the high levels seen in 2017.
As a result, Turner & Townsend’s latest UK market intelligence report finds that half of contractors (50.5%) surveyed were experiencing lukewarm tendering conditions, reporting increased competition and moderate price growth.
The trends are hurting profit margins. The analysis shows median margins for tier one contractors standing at 3% and 5% for tier two contractors.
Since the start of 2016, median tier one margins have shrunk by a quarter and tier two margins by half, leading Turner & Townsend to warn of a heightened risk of insolvency.
Paul Connolly, UK managing director of cost management said contractors and clients “need to have their eyes on the pressure points that could push parts of the supply chain to the edge”.
“So much rests on the Brexit withdrawal agreement and there remain risks of further decreases in demand, coupled with increases in the costs of materials and labour from the continent and elsewhere. Contractors’ already-thin margins could clearly come under further pressure.
“It’s essential for clients to be proactive about these risks – monitoring for warning signs, undertaking wide-ranging due diligence during procurement, and using project controls to pre-empt and correct problems at an early stage. It’s about checking and challenging the supply chain, but also collaborating – understand suppliers’ pressures and concerns, as well as holding them to account.”
Turner & Townsend’s report outlines the steps clients should take in terms of watching for warning signs, due diligence, pre-emption of problems, and creating a resilient client-supplier dynamic.Â
Image: Insolvencies on the rise (Turner & Townsend)
Comments
Comments are closed.
More scaremongering from the big-boys. The only people who are going to lose out are those profiting from cheap foreign labour, and depending on monopolising the property market with foreign investment coming from the gravy train brigade. Simple as that.